Solar

From Media for Unladen Swallow
Revision as of 23:42, 11 September 2026 by Hutchinsel (talk | contribs) (Publish Solar Array & Aft Arch draft)

Part of the Refit - 2025/ 2026 series. Draft — Lee to review. As-built to the September 2026 break; the array was still being re-configured at that point (see the box at the bottom).

The aft arch does a lot of jobs on this boat. It carries about 4 kW of solar, lifts the dinghy, mounts the RADAR, Starlink, a security camera, the stern nav light, the life-raft cradle, two scuba-tank holders, rod holders for trolling, and — eventually — two hanging chairs. It is also the single biggest visual change to the boat, and the thing that fought us the hardest.

The design

The structure is three arches and a set of legs, built by Atlantic Towers:

  • the main arch, which carries the aft half of the solar grid
  • a forward hinging arch that carries the front half of the grid and folds up so we can reach the panels
  • the dinghy-lift arch
  • support legs for the forward arch

The cockpit hardtop is a separate Atlantic Towers piece on its own legs, with a purpose-built ladder whose odd shape is deliberate structural triangulation. It carries a second, smaller bank of flexible panels.

Above the arch: RADAR, Starlink, camera, GPS/satellite compass (MSC 10), rig light, VHF antenna, and the nav-light mount. The boom was raised 3 feet to clear the arch. The split backstay passes through the plane of the array about 25 inches forward of the chainplate, which drove a lot of the geometry.

Build photos: see the AFT Arch gallery.

The solar array

Ten 300 W rigid panels on the arch grid plus the hardtop panels, for a design total around 4–4.5 kW, split into strings by voltage and current and fed to three Victron SmartSolar MPPT controllers (150/85, 150/60, 150/45). See Electrical for the charging side.

Real-world: on a partly-cloudy New Orleans afternoon, about 3.4 kW off a 4 kW ceiling — 85 percent efficient — and better expected further south.

What went wrong

Almost everything, in sequence:

  • The grid frame arrived sized for 8 panels, not the 10 we ordered. Then the actual panels measured up to 3 inches off their published dimensions. We re-designed the frame, drilled 400-plus holes on a benchtop drill press, and ate about $600 in extra aluminum bar.
  • The hardtop's corners got over-rounded in design, so 2 of the 100 W hardtop panels lost their space — the original 4×100 + 4×200 plan became 2×100 + 4×200.
  • On first power-up the panels made voltage but almost no current. A day of settings changes, firmware updates and phone calls with the battery engineers ended when we discovered the solar cutoff fuse had never been installed — we'd left it out deliberately as a safety measure and then forgotten. Fuse in, power flowed.
  • Full power the second time took another day-plus of troubleshooting before we found two connectors made months earlier that were never seated internally — the pins pulled straight out when we separated the housings.
  • Two panels then failed with burn-through. The maker (Bouge RV) blamed shading from the RADAR dome; we were skeptical. The replacements they sent were electrically different and physically wider and shorter, and didn't fit. As of the September break we were re-engineering the array again: a clean row of four new-size panels, the rest re-arranged, and — finally — the inline blocking diodes on every paralleled string that should have been in the design from the start. About $40 of parts turned into nearly $1,000 of rework because no one flagged it early.

The forward two hard panels weren't bolted down until 22 July 2026 — they had been blocked by the standing-rigging install for months, and had originally shipped in June 2025.

Access

The two centre panels of the ten are hinged so they lift for cleaning and maintenance from above. There is a telescoping aluminium plank and a telescoping ladder aboard for reaching the outboard parts of the structure, and a fold-down step or two on the mast for the same reason higher up.

Still open (September 2026)

  • Final wiring and test of the re-configured array
  • Longer power cables for the two hinged panels
  • Blocking diodes on each paralleled string
  • Full bolt-down of the replacement panels
  • Bouge RV warranty claim on panel #3
  • Confirm the final panel count, sizes and MPPT assignment for the as-built diagram

Diagrams to attach (from solar design.pptx / solar.xlsx): arch geometry with backstay clearance · array electrical configuration (strings → MPPTs) · panel layout on the grid and the hardtop.