Ground Tackle

From Media for Unladen Swallow
Revision as of 18:43, 28 September 2026 by Hutchinsel (talk | contribs) (Add the remaining Facebook build-log photos Lee approved (review sheet))
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Part of the Refit - 2025/ 2026 series. Draft — Lee to review. As-built to the September 2026 break.

Three anchors aboard, plus the dinghy's own — the philosophy being a bigger boat means more ways to need ground tackle, not just a bigger primary.

Description

Before and after

Before After

The original windlass

The rebuilt windlass, 2 Mar 2026

The original primary chain, rusted

The new stainless chain, 14 Mar 2026

As found — earlier photos (10)

Primary anchor

A 77 lb Ultra (Ultramarine) stainless with a flip swivel — a newer design than the Rocna carried on the Beneteau, and correctly sized for a 37,000 lb boat (the Beneteau's 55 lb was undersized here). Primary rode is 300 ft (about 90 m) of ⅜" (10 mm) stainless chain — the largest size the Maxwell 2200's gypsy can take, not a free choice. Periodic end-for-end reversal keeps the heavily-worked anchor-end sections from wearing out first.

Loading the chain (13 Jun 2026 below) revealed the chain locker has the volume but not quite the depth for the chain-pipe geometry — the fix in practice is placing the first 150 feet around the locker perimeter by hand so the rest flows freely. Making it fully self-stowing would have meant another foot of locker depth and giving up sail-locker space — not worth it.

The bitter end of the primary rode is tied to a bulkhead pad-eye with a bowline — line rather than a shackle so it can be cut with a knife if we ever have to abandon the anchor and chain for the safety of the boat.

Note: the windlass line-drum, the bowsprit and the primary chain pipe all end up on the "wrong side" for a perfectly clean bow layout. It works, but not as tidily as it should — fixing it would have meant more hull rebuilding than was worth it.

Backup bow anchor

A Mantus, roughly a 55 lb (exact model still to confirm). Rode is galvanized chain — somewhere in the 75–100 foot range, cut from 250 feet that came with the boat, the exact current length not being something we track closely — spliced to 200 feet of new line, since the old Beneteau line wouldn't fit the chain pipe and was too stretched past splicing anyway. Unlike the primary, this one doesn't get reversed on a schedule — it's a backup, rarely deployed.

Stern kedge

A Fortress — the aluminum, bolt-together design, disassembled and stowed when not in use. Some chain is reserved for it. The line is deliberately TBD: no dedicated line is planned for it right now — whatever's on hand at the time it's actually needed is the plan.

Snubber

A Suncor chain hook on nylon legs, with a fire-hose chafe wrap where the legs cross the toe-rail fairleads.

Windlass

The boat's Maxwell 2200 windlass, rebuilt rather than replaced — a modern equivalent is over $7,000; we have about $500 in the rebuild. The teardown, keyway damage and resleeving are in the build log below (Jun 2025 and Feb 2026).

The dinghy's ground tackle

The tender carries its own small Mantus ground tackle, separate from the boat's primary — see Dinghy & Davits.

Plan

None written up yet. (Lee to add.)

Outcome

Status is current to the September 2026 break. The dated detail — what broke, what got rebuilt, what we tested — is in the build log below.

Still open (September 2026)

  • Confirm the Mantus backup anchor's exact model/weight and current rode length
  • Stern kedge line — not yet decided or aboard

Lessons learned

None written up yet. (Lee to add.)

Build log — Lee's Facebook posts, verbatim

The paragraphs below are copied directly from Lee's own Facebook posts during the build (typos included) — not a paraphrase. Dates are the post date, not always the exact work date.

21 May 2025: Once we were settled, we got wooden stairs for the back so getting on and off is much safer. I then dumped the anchor Road overboard so it could be assessed and also get it out of the way so we could remediate the anchor/ sail locker area after the termites ate most of the wood in that area. Neither the primary or the backup anchor road was fit for use as configured. The primary anchor road consisted of maybe 50' of chain backed by 200' of 5/8' triple braid. Not my first choice for a primary ground tackle, but as I dumped the line overboard, I discovered rust imbedded in the line and saw at least 1 place where the line was badly abraded and then to top it all off, the screw/ pin that connected the chain to the anchor swivel was missing one side. There were many ways this ground tackle was ready to fail. So I turned my attention to the 2nd set of ground tackle. This one was all 3/8 chain, so far so good, until as I got the end (I was pulling from the ground) when the bitter end comes down on top "of me". It was not connected to the boat. I then turned my attention to cutting the remaining termite damage from the chain locker. There is a cross member that the windlass is bolted to that is likely damaged, but that will have to wait til I can unbolt the windlass. Now that the anchor road is on the ground, I can likely do that in the next week or so, when a fork life is available to lift it off the boat. So maybe tomorrow I will go back to making progress on the inside or the windlass - we'll see.

24 May 2025: We also finally decoded the Windlass circuit and have a plan to reconstitute it.

2 Jun 2025: More dissassembly today. The windlass is off the boat and ready to be rebuilt. The remaining headliner has also been removed. Finally, we removed the copper tubing that carried the refrigerant from the compressors to the cold plates. With the windlass out of the way, we can remove the mounting plate and decide the plan going forward to rebuild the whole sail/ chain locker area.

3 Jun 2025: We spent what was left of the morning cleaning out the debris in the sail locker and cutting the next layers of termite damage away. There may be another layer to go down low, but it is sufficient right now to its purpose. Having said, that we are likely going to redesign this entire area as we want to have a primarily chain anchor road and as we found the boat, there is not room to accommodate the length we want. (Chain needs a fairly deep hole to pile up in as it tends to pile into a cone and does not spread out easily). I also started to disassemble the windlass. I need to study the parts diagram to understand how to take it apart beyond this point. The good news is we were able to understand why one side was not spinning freely and it's a simple matter of cleaning and lubrication. We also sold a few more items including the old windlass and anchor.

4 Jun 2025: OK no pics today. We spent 3 hours taking apart the windlass. The gear box is fine, but the shaft that runs through it was too tight. It was a serious battle to remove it so we could do the test of the service. So once we got it all apart, we decided that the bushings involved were scared [scarred]. We also cleaned up the shaft and decided it's surface needed some TLC. So in pieces it's going to a machine shop to have a cleanup. It may be fine as is, but the maintenance schedule requires it to be disassembled every so often and this was way too difficult so it's getting machined back to tolerance. We'll also have the housing painted when they do the deck. We'll do the seals, oil and grease once it is in better shape. Nothing wrong inside the gear housing.

10 Jun 2025: In a pleasant surprise the windlass is back from the machine shop and everything fits/ spins much better now.

14 Nov 2025: The Sr fiberglass guy was back working on the bow sail/ anchor locker. We got the plumbing in the fwd port berth to the point where I need the yard to wrap up some of thier stuff next. This includes the water maker. I need to install the fresh water system next to wrap up the water maker. While we were in places where people aren't meant to be, I also got the new solinoid for the windlass installed. Once the chain locker and windlass support is done, we can start reassembling the ground tackle. Finally, we received a 77lb package containing our SHINNY new UltraMarine Stainless steel anchor. Sorry no pic as the yard put it away before I got a picture. This is a newer technology than the Rocnar anchor on the Beneteau. Had that anchor been sized OK for this boat, we would have kept it, but 55 lbs was too small fir the primary anchor on this boat.

26 Nov 2025: Well the promised photo dump was OBE. I did get a pic of the new anchor though.

9 Feb 2026: While we are waiting for some hinges and manlift time, we moved our efforts to the bow. While Brownie Hutchins sanded and painted i started reassembling the windlass. More work on both tomorrow, but I now know how it goes together. I ordered new mounting bolts so we have to wait for their arrival and then we can do the next step in reassembling the bow.

10 Feb 2026: While attempting to reassemble the windlass to make sure I had everything and it all worked, I discovered the friction clutches/ cones in the assembly had damage around their keyways. They have been sent out to be cleaned up and new keyways cut. This is likely why one side didn't release properly back when we tried to pull the chain out of the boat.

14 Feb 2026: I switched gears and decided to work on assembling the bow area. "The chain locker is painted" i was told - i know i needed to pump out the bottom as it has been collecting water for several months. After pulling out the test chain for the new chain pipe i discover that no it hadn't been painted. No sense doing plumbing - stop everything, (I'd already pumped it out) and powerwash it as it was full of fiberglass dust repump it - oh wait the pumps impeller is done (it was on it's last legs last time) so I had to sponge out 3 gals of water and debries. Had they told me it still needed painting prior to installing the chain pipe it would have been challenging, but not miserable to reach everything to paint that area. But no the chain pipe is now square in the middle of the hatch space (as intended) so squeezing me in there to paint everything including the bare glass under the sail locker floor was unnecessarily miserable. It's done now. I did start the process on plumbing in the anchor wash line, but the Bulkhead fitting i purchased (months ago) wasn't intended for a bulkhead this beefy. I have to eat that cost as we are way outside of Amazon's return windows due to the yard's failure to make progress there. We will 3'd print a fitting as finding something commercially available will be difficult.

2 Mar 2026: Ok so I got about half a day of yard help today. Made decent use of the help: windlass is sitting on its mounting platform (i need to wire it up before final mounting). The diagonal support to stiffen the RADAR mount is installed. About half of the remaining solar panel bokts are installed.

11 Mar 2026: We made some more progress outside terminating wires and mocking up the new helm station. Also installed the pad eyes that the anchor road will be fastened to. My anchor road will be attached to my boat....

12 Mar 2026: Today's installment is all about wiring. First of all with the arrival of our anchor chain being imminent a working windlass is becoming a critical path item. The windlass consumes ALOT of amps in short bursts. So much so that regular switches would melt. So there is a solinoid in the wiring schematic. There are 2 sides to this device. The first side has 3 connections for the battery power in and the 2 positive outs. This is 2/0 gauge wire. The motor direction is determined by which of the 2 outs gets power. The second set is the control lines. A neg and 2 positives. This is where the remote switches connect in. Again which ever side sees power closes the soliniod on that side sending power to the windlass. In a setup like ours where there is more than 1 set of up/down switches, the power that gets routed through the up/down switches is often drawn from the battery connection via a much smaller gauge wire on the soliniod and routed to both sets of switches. I was expecting this configuration. Not what I found. There was a 4th wire that was connected to the battery connection and the lines providing the power to the switches where just tied together. WTF. After 30-45 mins tracing wires we found both the 4th wire (yellow) and 1 of the 2 wires that were tied together (blue) both unterminated in the power patch bay. Wires 1 and 2 trucked right on through as I would have expected. So we opted for a safer (more correct) approach of providing power to the blue lines from a fused point in the patch bay and removing the yellow completely. I did find our barrel of chain in the workshop as even though it was clearly labeled and you'd think a boatyard would recognize a barrel of anchor chain and leave it by the boat since I have laid out everything before lunch in anticipation of a working windlass and a barrel of chain being delivered. I guess I will see if someone can use a forklift to move the chain tomorrow (100m of 3/8 chain) as it won't be moving that on my own.

13 Mar 2026: Ok it's been an interesting couple of days.

14 Mar 2026: Otherwise the chain is out of the barrel and all marked and hooked and ready to be loaded.

16 Mar 2026: Well today was a swing and a long foul ball twice. Walked away from the plate before a complete strike out. We started by checking out the 3-d printed panel for the very back of the chain locker. Got the cutout dims wrong - just a 1/2 inch off. Jig saw solved that one. The anchor is loaded for now. So the 2 planned tasks today didn't close as expected...

4 Jun 2026: Today's focus was installing thru hulls. We got everything we had parts for in before lunch (8 of them) We then moved up to the chain locker for v2 of the chain pipe. Needed parts, moved on. We got the parts for the chain locker tonight, we'll see how the metric bolts go tomorrow...

11 Jun 2026: We also successfully got the partially assembled back up anchor on the bow tonight. Everything up there is reverse how it should be based on the windlass configuration (line drum on the wrong side) and the anchor bow sprit configuration and finally the chain pipe for the primary anchor are all on the wrong side for it to all fit cleanly together. We would have had to do major rebuilding of tge hull far in excess of what we already did to make it all fit right. It will work, but not as cleanly as it should. Our wayward UPS package mysteriously appeared at the boatyard today so we were able to get the last 3 holes filled in with their intended items so other than a drillbit hole that needs to be filled our below tge waterline work is done.

13 Jun 2026: "Easy" day today. We got the last part of the chain pipe in and dumped the chain overboard, added the last 2 pieces and pulled it back on board. I placed the first 100-150 feet around the exterior of the chain locker and let the last 150 ft or so pile up in the center. Between adjusting the angle and discharge point over the chain locker of the pipe and placing the 1st 150' of chain "out of the way" the rest came in without jamming the works up. If you are questioning the long term viability of having to place some of than "manually" you are right - not ideal, but i don't expect to have more than 150' out in most circumstances so the extra chain that I placed won't come out too often. I will have to deal with placing it if I do need the extra length. To be completely on its own, the chain locker would have needed to be another foot or so deeper than it is and I needed to leave space in the sail locker for sails.... I need to now reattach 3 pieces of molded fiberglass around the bow area and we can call this part of the job done.

2 Jul 2026: 5. The fittings on the anchor wash pump where leaking. Tightened them up.

29 Jul 2026: I also wrapped up most of the bow work by reinstalling the 3 pieces of fiberglass that covered the upper chain locker and the windlass. We are missing the last hinge.