Dinghy & Davits

From Media for Unladen Swallow

Part of the Refit - 2025/ 2026 series. Draft — Lee to review. As-built to the September 2026 break; passage-rail engineering still in progress.

The tender is a Caribe DL10 RIB with Hypalon tubes, powered by a Momentum M10 electric outboard — no gas aboard to store or spill, in keeping with the rest of the all-electric systems. It carries its own small Mantus ground tackle, separate from the boat's own — see Ground Tackle.

Description

Before and after

Before After

The dinghy in its shipping crate

Coconut at the slip with the electric motor and name decals, 8 Aug 2026


The lift

The dinghy lift lives on the dinghy-lift arch, part of the same three-arch structure that carries the solar array (see Solar). Lee installed the lifting tackle solo on 30 January 2026 (see build log below) and it has worked since.

Passage stowage

The lift isn't where the dinghy rides offshore — a following sea reaching it there could put it straight into the solar array — so for passages it comes down onto the deck above the aft berth instead, held by a set of purpose-built passage-storage rails. The first version (16 August 2026, build log below) is a starboard-side proof of concept; final engineering (pivot/removable/lockdown) was still open at the September break.

The lazarette hatch handles took some collateral damage from this arrangement — the dinghy lashes down directly over them on passage, which isn't an ideal placement but works.

Photos: dinghy-lift install (30 Jan 2026) · passage-storage rails, v0.5 (16 Aug 2026).

Plan

Version 2 is going to focus around a removable I-beam to carry a trolley that a block system will be fastened to. The blocks will lift the dinghy out of the water (likely with the help of the existing lift) and then slide the hoisted dinghy forward to then be lowered on the rails from V1.

      • pics needed

Outcome

Status is current to the September 2026 break. The dated detail — what broke, what got rebuilt, what we tested — is in the build log below.

Still open (September 2026)

  • Passage-rail engineering — final pivot/removable/lockdown design

Ongoing watch list (from the maintenance plan): tube UV shield and Hypalon condition · valve service and tube pressure · lifting-tackle lines, shackles and hinge pins · aft deck tie-down pad-eyes and straps before every passage · outboard shaft checked for fishing line/weed wraps · fresh Momentum M10 shaft-casing washdown and periodic idle-run if it's sat unused.

Lessons learned

None written up yet. (Lee to add.)

Build log — Lee's Facebook posts, verbatim

The paragraphs below are copied directly from Lee's own Facebook posts during the build (typos included) — not a paraphrase. Dates are the post date, not always the exact work date.

14 Aug 2025: The next piece of the puzzle has arrived. Yup an electric Outboard motor. Battery pack is separate. Goal is to not need gasoline on the boat.

19 Dec 2025: We then turned our attention to the primary support arch/frame for the solar array, dinghy lift etc. This is quite the science project as it is all angles. After 3 cuts and 5 lifts it is now cut to size and it is basically level side to side and level front to back. We ran out of work day to start anchoring it to the boat. That will take most of tomorrow morning.

30 Jan 2026: I got the dinghy lift installed yesterday. I was waiting on yard help (a lift) and some 3-d printing. We'll the 3-d printing finished but no yard so I used some Yankee enginuity and successfully did it myself. See pic. I still need the lift to drill some holes, but that will likely happen when we mount the solar array. See pic

24 Feb 2026: The pic is the new handle(s) for the lazzarrette hatches. One of the old latches broke so replaced both of them. Dremel with a full assortment of accessories made the job much easier as the existing cutout as a 1/4" too small. Their placement is not ideal as the lever underneath is far to short to engage anything to lock them down. Fortunately the dinghy will be lashed on top of them for passages so no worries about them coming open at an inopportune time.

13 May 2026: We got 3/5 of the bottom paint on today. Also started working with a sheet of starboard ($650 worth). This will provide new bases for the 2 toilets. Additionally, we started working on the dinghy rails for the dinghy while we ate on passage. We'll get some pics once we get a bit further along in the fabrication process.

5 Jun 2026: We finally dug the dinghy out of storage and inflated it for the 1st time yesterday. This morning 2 of the 3 air cells were no longer at full pressure (the bow barely had any air in it). Local dealer is aware and we are awaiting a get well plan. We bought the dinghy a year ago.

30 Jun 2026: The dinghy also needs it's final outfitting and then it can sit in the water nearby until we are ready to bring it up onto its davits. Right now it would be in the way for getting on/off the boat.

1 Jul 2026: We also finally mounted the motor on the dinghy. The battery still needs to be strapped down, but that is straight forward.

1 Aug 2026: We have to do some work to integrat the 2 new panels electrically and then wrap up 3 more connections on the back (stern Nav light, Radar power and our dinghy alarm loop).

16 Aug 2026: So tonight's update includes work to store our dinghy on our AFT deck while in passage mode and continued working towards brining more of our electronics online. I'l post pics of the dinghy mount in the next week or so.

21 Aug 2026: I did get the Dinghy tasks (secure miyor battery, mount dinghy night navigation light base) done.


Additional photos from the same posts (no dated log entry to attach them to):


Additional photos (from the phone; also on Facebook):